What is the purpose of a burndown chart in Scrum?

  • To monitor team productivity
  • To track the number of tasks completed
  • To track the time spent on each task
  • To visualize progress towards completing the sprint backlog
The purpose of a burndown chart in Scrum is to visualize progress towards completing the sprint backlog. It tracks the remaining effort (usually measured in story points or hours) over the duration of the sprint. This chart helps the Scrum team and stakeholders understand if they're on track to complete the committed work by the end of the sprint.