During Sprint Planning, the Scrum Team estimates the effort required to complete _______ items.
- User stories
- Epics
- Product Backlog items
- Sprint Backlog items
The correct option is "Product Backlog items". During Sprint Planning, the Scrum Team estimates the effort required to complete the Product Backlog items selected for the Sprint. This estimation helps in planning the work for the upcoming Sprint.