How can you interpret a Burndown Chart in terms of project progress and performance?

  • By analyzing team member availability
  • By assessing project risks and uncertainties
  • By comparing planned work with completed work
  • By tracking project budget and expenditures
A Burndown Chart allows project teams to interpret project progress and performance by comparing planned work with completed work over time. It provides insights into whether the team is on track to meet project goals and deadlines, helping identify potential issues early for timely resolution.