Your Agile team is using a burndown chart to track progress. In the middle of the sprint, the burndown chart shows an upward trend. What action should the team take based on this metric?
- Decrease the sprint scope
- Extend the sprint duration
- Identify impediments and remove them as soon as possible
- Increase the sprint backlog
An upward trend in the burndown chart during the sprint indicates that the team is not progressing as planned and might face obstacles or impediments. In this situation, the team should proactively identify any blockers or issues hindering progress and take immediate action to resolve them. By addressing impediments promptly, the team can regain momentum and strive to achieve the sprint goals within the allocated time frame.
Loading...
Related Quiz
- When might you use "blocks" as an issue link type in JIRA?
- Your company has acquired another large company, and you need to integrate their JIRA instance with your existing one. What strategies would you employ to ensure smooth integration and scalability?
- What Agile metric is used to measure the frequency of releases or deployments?
- Can JIRA plugins and add-ons be developed by third-party vendors, or are they exclusively developed by Atlassian?
- What is the purpose of a project's "Components" in JIRA, and how can they be managed?