Your Agile team is using a burndown chart to track progress. In the middle of the sprint, the burndown chart shows an upward trend. What action should the team take based on this metric?

  • Decrease the sprint scope
  • Extend the sprint duration
  • Identify impediments and remove them as soon as possible
  • Increase the sprint backlog
An upward trend in the burndown chart during the sprint indicates that the team is not progressing as planned and might face obstacles or impediments. In this situation, the team should proactively identify any blockers or issues hindering progress and take immediate action to resolve them. By addressing impediments promptly, the team can regain momentum and strive to achieve the sprint goals within the allocated time frame.