What is the purpose of a burndown chart in Agile?

  • To measure the team's speed in completing tasks
  • To monitor the number of defects found in each iteration
  • To track the total number of tasks completed in a project
  • To visualize the amount of work remaining in a sprint
The purpose of a burndown chart in Agile is to visualize the amount of work remaining in a sprint. It helps teams track their progress and identify any deviations from the planned work, enabling them to take necessary actions to stay on track.