What is the primary goal of Sprint Planning in Agile Scrum?
- To conduct a retrospective on the project
- To define the work to be accomplished in the Sprint
- To prioritize the product backlog
- To review the work completed in the previous Sprint
Sprint Planning in Agile Scrum involves defining the work to be accomplished in the upcoming Sprint. This includes selecting User Stories from the Product Backlog and breaking them down into smaller tasks that the team can commit to completing within the Sprint duration.