During Sprint Execution, if a team member becomes unavailable due to unexpected circumstances, how should the team respond?
- The team should continue with the Sprint without making any changes.
- The team should extend the Sprint duration to accommodate the missing team member's absence.
- The team should reassess the Sprint goals and adjust accordingly.
- The team should wait for the member's return before proceeding with any work.
If a team member becomes unavailable during Sprint Execution, it's crucial for the team to reassess the Sprint goals and adjust their plans accordingly. This might involve redistributing tasks among the remaining team members or reprioritizing the backlog items to ensure the Sprint goals can still be met. Adaptability is key in Agile methodologies.
Loading...
Related Quiz
- In a JIRA workflow, what is a "resolution"?
- Scenario: You are managing a software development project in JIRA, and there is a critical bug that needs to be fixed before any further work can proceed. Which issue link type would you use to indicate that the bug "blocks" other issues in the project?
- What type of software is JIRA?
- What is velocity in Agile project management?
- Scenario: In a JIRA project, you notice that team members are not following the agreed-upon naming conventions for issues. What steps would you take to ensure compliance with these conventions?