What is the purpose of a Release Burndown Chart?
- To analyze the distribution of tasks across sprints
- To monitor team velocity over time
- To track the remaining work in a release
- To visualize the progress of user stories in a sprint
A Release Burndown Chart is used to track the remaining work in a release over time. It helps the team understand if they are on track to meet the release deadline by showing the progress of completing user stories or tasks planned for the release.