Scenario: During a sprint, the team encounters unexpected technical challenges that increase the amount of work required to complete the user stories. What impact would you expect to see on the Sprint Burndown Chart?

  • The burndown chart will show a flat line indicating no change in work remaining.
  • The burndown chart will show a fluctuating line indicating unpredictable progress.
  • The burndown chart will show a shallower slope indicating decreased work remaining.
  • The burndown chart will show a steeper slope indicating increased work remaining.
If unexpected technical challenges arise during a sprint, it will likely increase the amount of work remaining, leading to a steeper slope on the Sprint Burndown Chart. This indicates that the team is facing difficulties in completing the planned work within the sprint timeframe.