The _______ chart is used in Agile to visualize the amount of work remaining in a sprint.
- Bar
- Burndown
- Pie
- Scatter
The correct answer is "Burndown". A burndown chart tracks the remaining work in a sprint. It displays the amount of work remaining to be done versus time, allowing the team to track their progress and adapt accordingly.