What is the primary purpose of a Burndown Chart in Agile project management?

  • To allocate resources effectively
  • To manage team conflicts
  • To track the progress of work completed in a sprint
  • To visualize the remaining work in a sprint
A Burndown Chart in Agile project management primarily visualizes the remaining work in a sprint, helping the team to understand their progress towards completing the planned work. It assists in identifying whether the team is on track to complete the sprint commitment.