A Sprint Burndown Chart helps teams track their progress towards completing _______.

  • Planned Work
  • Remaining Work
  • Completed Work
  • Additional Work
The correct option is Remaining Work. A Sprint Burndown Chart helps teams track their progress towards completing the remaining work in the sprint backlog. It shows how much work is remaining to be done as the sprint progresses, enabling teams to adjust their efforts and ensure they meet their sprint goals.