How can you track the progress of a specific version or sprint in JIRA?
- By accessing the JIRA marketplace
- By creating a new project
- By updating the JIRA settings
- By using the Burndown Chart
You can track the progress of a specific version or sprint in JIRA by using the Burndown Chart. This chart visually represents the amount of work completed versus the amount of work remaining over time, providing insight into the team's progress and velocity.