What does it indicate if the actual work remaining line in a Burndown Chart is above the ideal line?

  • The team has completed all the work
  • The team is ahead of schedule
  • The team is behind schedule
  • The team is exactly on schedule
If the actual work remaining line in a Burndown Chart is above the ideal line, it indicates that the team is behind schedule. This means that the team is not completing work at the expected rate, and adjustments may need to be made to ensure that the sprint goals are met on time.