What does it indicate if the actual work remaining line in a Burndown Chart is above the ideal line?
- The team has completed all the work
- The team is ahead of schedule
- The team is behind schedule
- The team is exactly on schedule
If the actual work remaining line in a Burndown Chart is above the ideal line, it indicates that the team is behind schedule. This means that the team is not completing work at the expected rate, and adjustments may need to be made to ensure that the sprint goals are met on time.
Loading...
Related Quiz
- What elements should be included in an issue name to make it informative?
- In a large team, it's essential to establish clear _______ to prevent chaos.
- How can you change the assignee of an issue in JIRA?
- Scenario: You are a JIRA administrator, and a team member needs to find all issues that were resolved in the last two weeks. Which JIRA feature or functionality would you guide them to use?
- Scenario: You have a JIRA project for software development, and you want to implement a workflow that enforces code review before an issue can move to the "Done" status. What workflow element would you use to accomplish this?