Scenario: In a Release Burndown Chart, the actual work remaining line is consistently above the ideal line. What does this suggest about the progress of the release?

  • The release is ahead of schedule, and the team is working faster than anticipated.
  • The release is at risk of being completed early, and additional tasks need to be added.
  • The release is behind schedule, and more work needs to be done to catch up.
  • The release is progressing as expected, and the ideal line represents an unrealistic goal.
When the actual work remaining line consistently lies above the ideal line on a Release Burndown Chart, it suggests that the release is behind schedule. This indicates that the team is not completing work at the expected rate, and corrective actions may be necessary to ensure timely delivery.