What type of information can be obtained from a Sprint Burndown Chart?
- Future sprint planning details
- List of team members and their roles
- Progress of work completed versus work remaining over time
- Total number of tasks in the sprint
A Sprint Burndown Chart provides information about the progress of work completed versus work remaining over time. It visually represents how much work has been completed each day compared to the total amount of work planned for the sprint. This helps teams track their progress and identify any deviations from the sprint plan, allowing them to make necessary adjustments to meet their goals.