What is the recommended approach for handling unfinished work at the end of a Sprint?

  • Increase the team's capacity to complete the remaining work.
  • Inform stakeholders that the work couldn't be completed.
  • Integrate the unfinished work into the next Sprint backlog.
  • Leave the unfinished work for a future Sprint.
The recommended approach for handling unfinished work at the end of a Sprint is to integrate it into the next Sprint backlog. This ensures that the work isn't lost and provides an opportunity for the team to complete it in a future iteration. It's essential to maintain transparency with stakeholders about the unfinished work and incorporate any feedback or lessons learned into future planning.