What is the recommended approach for handling unfinished work at the end of a Sprint?
- Increase the team's capacity to complete the remaining work.
- Inform stakeholders that the work couldn't be completed.
- Integrate the unfinished work into the next Sprint backlog.
- Leave the unfinished work for a future Sprint.
The recommended approach for handling unfinished work at the end of a Sprint is to integrate it into the next Sprint backlog. This ensures that the work isn't lost and provides an opportunity for the team to complete it in a future iteration. It's essential to maintain transparency with stakeholders about the unfinished work and incorporate any feedback or lessons learned into future planning.
Loading...
Related Quiz
- The JIRA "Backup Manager" provides options for scheduling _______ backups.
- You are responsible for ensuring that only a select group of users can access sensitive financial data in JIRA. Which aspect of JIRA's user management system would you focus on?
- A "Shared Configuration" in JIRA allows you to reuse _______ across multiple projects.
- To automate repetitive tasks in JIRA, you can use _______ to trigger actions based on specific events.
- Scenario: Your team uses JIRA for project management, and you want to automate the process of assigning issues to team members based on specific criteria, such as issue type and priority. Which JIRA Automation component would you use to achieve this?