Which method is commonly used for forecasting project costs?

  • Bottom-up estimation
  • Top-down estimation
  • Random guessing
  • Historical data analysis
Bottom-up estimation involves estimating individual project components and aggregating them to determine the total project cost. This method provides a detailed and accurate forecast by considering specific project requirements and potential risks, improving cost estimation accuracy.