Which technique is commonly used for time estimation in project planning?
- PERT (Program Evaluation and Review Technique)
- SWOT analysis
- Fishbone diagram (Ishikawa diagram)
- Kanban
PERT (Program Evaluation and Review Technique) is a widely used technique for time estimation in project planning. It involves analyzing optimistic, pessimistic, and most likely time estimates to calculate a realistic timeline.