How do you prioritize risks in a risk management plan?

  • Assessing the impact and likelihood of each risk
  • Ignoring risks with low likelihood
  • Addressing risks randomly
  • Prioritizing risks based on team hierarchy
Prioritizing risks involves assessing both their impact on project objectives and the likelihood of occurrence. This allows the team to focus on mitigating high-impact, high-probability risks first, maximizing risk management effectiveness.