What are test closure activities primarily concerned with?

  • Evaluating overall project performance
  • Executing test scripts
  • Identifying bugs and defects
  • Writing test cases
Test closure activities primarily focus on evaluating the overall project performance against the defined objectives. This involves analyzing test results, assessing test completion criteria, and ensuring that the testing process aligns with project goals before concluding the testing phase.