In a fast-paced Agile project, how should ETL testing be adjusted to accommodate a sudden change in data source formats?
- Collaborate with stakeholders, update test cases, and perform exploratory testing to validate the changes
- Modify existing test cases to accommodate the new data source formats
- Postpone testing until the next sprint to avoid disruption
- Skip testing for the impacted data sources to maintain project timelines
In a fast-paced Agile project, adapting to sudden changes in data source formats requires collaboration with stakeholders, updating test cases, and performing exploratory testing to validate the changes. This ensures that testing remains effective despite evolving project requirements.
Loading...
Related Quiz
- In ETL testing, the use of __________ can significantly reduce the risk of data corruption during transformation.
- ________ is a key metric that measures the percentage of test cases executed in the ETL process.
- In ETL, ________ testing is crucial for verifying the transformation rules.
- What role does the ETL mapping document play in test requirement analysis?
- What is the primary goal of Test Data Management in ETL testing?