What is the difference between a risk and an issue in project management?

  • A risk has no impact on project objectives, while an issue does
  • A risk is a potential future event that may have a negative impact on project objectives, while an issue is a current problem that needs to be addressed
  • A risk is always positive, while an issue is negative
  • A risk is certain to occur, while an issue may or may not happen
In project management, a risk is a potential future event or condition that may have a negative impact on project objectives. An issue, on the other hand, is a current problem or concern that is affecting the project. Risks are uncertain events that may occur in the future, while issues are existing problems that need to be addressed immediately.