As a project manager, you're faced with conflicting reports on the project's progress. How would you analyze the data to determine the true status and take corrective action?
- Cross-reference data from multiple sources and verify accuracy
- Disregard conflicting reports and proceed as planned
- Hire an external consultant
- Rely solely on the report from the project sponsor
Cross-referencing data from various sources enables project managers to identify discrepancies and inconsistencies, ensuring the accuracy of information used for decision-making. This approach fosters transparency and accountability, facilitating informed decisions and timely corrective actions to keep the project on track. It reflects the Project Management Institute's emphasis on data-driven decision-making and risk management.
Loading...
Related Quiz
- _____ is a decision-making model that involves identifying goals, gathering information, identifying alternatives, evaluating options, and making a decision.
- What is the significance of maintaining eye contact during a conversation?
- _________ is a strategy used to mitigate resource constraints by outsourcing certain project tasks or activities.
- When faced with multiple options, what should be considered before making a decision?
- What is the importance of active listening in effective communication?