A _______ is a formal, approved version of a plan against which project execution is compared to measure and manage variances.

  • Baseline
  • Gantt Chart
  • Project Charter
  • Stakeholder Register
In project management, a 'baseline' is a crucial concept. It represents a formal, approved version of a project plan, which serves as a reference point to compare and manage variances during project execution. It includes key project elements such as schedule, scope, and budget. A Gantt Chart is a visual representation of a project schedule, a Project Charter is a document that authorizes the project's existence, and a Stakeholder Register is a record of project stakeholders.