A _______ is a formal, approved version of a plan against which project execution is compared to measure and manage variances.
- Baseline
- Gantt Chart
- Project Charter
- Stakeholder Register
In project management, a 'baseline' is a crucial concept. It represents a formal, approved version of a project plan, which serves as a reference point to compare and manage variances during project execution. It includes key project elements such as schedule, scope, and budget. A Gantt Chart is a visual representation of a project schedule, a Project Charter is a document that authorizes the project's existence, and a Stakeholder Register is a record of project stakeholders.
Loading...
Related Quiz
- In network security, the principle that states users should only have the permissions necessary to perform their job functions is called the principle of _______.
- The _______ in an operating system acts as a bridge between application software and hardware.
- _______ is a virtualization technology focused on running multiple instances or copies of an application on a single set of hardware resources.
- A project manager receives feedback from the quality team that certain features do not meet the quality standards. What should be the project manager's immediate step?
- When changes are proposed during a project, they're typically reviewed and either approved or denied by a group known as the _______.