You're managing a project and notice that one of the critical path activities is delayed. What is the most likely impact on the project?

  • Other project activities won't be affected.
  • The project budget will be reduced.
  • The project's duration will be extended.
  • The project's scope will be enhanced.
When a critical path activity is delayed, it can lead to an extension of the project's duration. The critical path represents the longest path in a project, and any delay in these activities directly affects the project's completion time. Other project activities may be delayed as well due to their dependencies on the critical path activities.