In IT project management, the total of the approved time-phased project budget, including all authorized contingency reserves, is known as _______.

  • Contingency Budget
  • Cost Baseline
  • Financial Snapshot
  • Project Quota
The term you're looking for is 'Cost Baseline.' In IT project management, the cost baseline represents the approved budget for the project, including all authorized contingency reserves. It's a critical component for tracking and controlling the project's financial aspects.