In IT project management, the total of the approved time-phased project budget, including all authorized contingency reserves, is known as _______.
- Contingency Budget
- Cost Baseline
- Financial Snapshot
- Project Quota
The term you're looking for is 'Cost Baseline.' In IT project management, the cost baseline represents the approved budget for the project, including all authorized contingency reserves. It's a critical component for tracking and controlling the project's financial aspects.
Loading...
Related Quiz
- In IT risk management, a(n) _______ is an unforeseen event that can have negative consequences for an organization's objectives.
- Which of the following best describes the term "risk appetite" in IT risk management?
- What is the primary purpose of a hypervisor in virtualization?
- With the rise of digital channels, a retail company wants to enhance its customer experience. What strategic initiative should they prioritize to achieve a seamless omnichannel experience?
- Which component of a computer temporarily stores data that the CPU is currently processing or using?