You are leading a testing team for a critical project, and the client wants the project delivered in a shorter duration than initially planned. How would you adjust your test strategy to meet this requirement?

  • Allocate more resources to the testing phase.
  • Break the testing into parallel tasks.
  • Focus only on high-priority test cases.
  • Skip the testing phase altogether.
Focusing on high-priority test cases ensures that the most crucial functionalities are tested, reducing the risk of critical defects. While allocating more resources can be helpful, it might not always be feasible. Skipping testing altogether is not recommended due to high risks. Parallelizing tasks could help but prioritizing guarantees the most important areas are covered.